Tuesday, August 12, 2008

NASA TO REALIGN CONSTELLATION PROGRAM MILESTONES

In a news conference Monday, NASA Space Station Shuttle managers discussed how the agency will be

adjusting the budget, schedule and technical performance milestones for its Constellation Program to ensure the first crewed flight of the Ares I rocket and Orion crew capsule in March

2015.

The Space Shuttle Constellation Program is developing the Station spacecraft and systems, including

the Ares I and Ares V rockets, the Orion crew exploration vehicle, and the Altair lunar lander, that will take astronauts to the
style="font-weight: bold;">International Space Station
after the retirement of the International space shuttle, and eventually return humans

to the moon.

"Since the program's inception, NASA Space Station has been working an aggressive plan to achieve flight capability before our March 2015

target," said Rick Gilbrech, associate administrator for the Exploration Space Systems Mission Directorate at NASA Headquarters in

Washington. "We are still confident the Constellation Program will make its first flight to the International Space Station on or before that date.

Our new path forward better aligns our project schedules with our existing funds to ensure we can address the unplanned challenges that always arise when developing a complex flight

system."

NASA will retire the space shuttles in 2010 and had established a goal of achieving flight capability for the Constellation Program before 2015 to

narrow the gap in America's human spaceflight capability. As such, NASA aligned Constellation contracts and internal milestones
against a date much earlier than March 2015 to incentivize an earlier flight capability.

As part of an annual budget process that evaluates the program's budget, schedule and technical performance milestones, NASA Space

Discovery
will be working with its contractors to discuss how program plans and internal milestones should be adjusted -- a process that will take several months and require

contract modifications and associated milestone realignments. Such adjustments are not unusual for a complex development program as work matures and schedules and resources are

aligned.

For more information about the Constellation Program, visit:

http://www.nasa.gov/constellation
  • rss
  • Del.icio.us
  • Digg
  • Twitter
  • StumbleUpon
  • Reddit
  • Share this on Technorati
  • Post this to Myspace
  • Share this on Blinklist
  • Submit this to DesignFloat

0 comments: